Shunt reactors are in high demand as grid-stabilizing components. However, testing them is much more demanding than testing transformers. Siemens Energy’s transformer plant in Dresden therefore relies on a new testing system from HIGHVOLT, which is the only one of its kind in the world.
Frank Wollmann, plant manager at Siemens Energy in Dresden, has plenty to do: The transformer plant’s order books are more than full. The approximately 240 employees at the site currently produce around 115 medium-power transformers and 25 shunt reactors every year.
And thanks to the energy transition, the equipment is in greater demand than ever before. The importance of shunt reactors – also known as compensating reactors – will continue to grow in the future as they compensate for reactive power, increase transmission efficiency, and regulate voltage at the same time. In short, they keep the grids stable.
In order to cope with the enormous increase in demand, Siemens Energy plans to expand its production in Dresden. Wollmann says: “We want to manufacture more transformers and at the same time increase the proportion of shunt reactors. To achieve this, we are expanding the plant step by step.”
“We want to produce more transformers and increase the proportion of shunt reactors at the same time.”
Frank Wollmann, Plant Manager at Siemens Energy in Dresden
Comprehensive testing program
A central component of this is the expansion of the existing test bay. Because whether it’s a transformer or a shunt reactor – before the colossi weighing several tons are sent to customers, they have to pass an extensive catalog of tests. “Depending on what additional requirements the customers have, these factory acceptance tests can take between two days and a week and a half,” says Wollmann. This is absolutely necessary because any undetected error could have fatal consequences later in operation.
However, the test facility in Dresden was not previously designed to carry out these tests on shunt reactors. High three-phase test voltages must be provided for them and the requirements for the tests with higher test frequencies are more complex. Previously, the acceptance tests were carried out at the sister plant in Nuremberg, but the process involved was too complicated and too expensive.
Siemens Energy therefore decided to upgrade the test field in Dresden. Wollmann only had to walk across the yard once to find a suitable solution: HIGHVOLT, a specialist in high-voltage testing technology and member of the Reinhausen Group, which is based on the same site as Siemens Energy. “There are only a handful of manufacturers in the world who can even build such systems,” says Wollmann.
Andreas Thiede from HIGHVOLT designed the test system for Siemens Energy.
Unique upgrade
Andreas Thiede is the expert for such AC voltage test systems at HIGHVOLT. Even though the basic principle of these systems is the same, every test system that he and his team design is unique.
However, the test system at Siemens Energy was also something special for Thiede: “We normally offer a container solution, but that was out of the question due to the structural conditions.” So space had to be created first: Two old generators were taken out of the basement, ceilings were lifted, and new floors were installed to accommodate components such as converters, capacitor banks, and, above all, the new 200 MVA extra-high voltage adapting transformer which supplies the test voltage of up to 360,000 volts required for the shunt reactors and was manufactured by Siemens Energy based on HIGHVOLT’s design specifications.
One special feature that HIGHVOLT has developed especially for Siemens Energy is a so-called DC extension which can be used to test how the inductance behaves with a gradual increase in voltage: “This additional device can be used to charge the shunt reactor with a direct current and thus simulate 150 percent operation, that is, even above the power limits of our AC voltage system,” explains Thiede.
More shunt reactors
When the testing system was finally ready for operation after just eleven months of construction, the shunt reactors were already queuing up. The system worked straight away and Wollmann is very satisfied: “With such a complex system, that’s not a given.
Of course, some fine tuning had to be done, but in the end the shunt reactors and transformers successfully left the factory and that’s what counts.” Grid operators can also be pleased: Siemens Energy can now offer significantly more shunt reactors.
Reinhausen Inside
The AC voltage test system developed for Siemens Energy consists of a converter, capacitor banks, a 123 kV matching transformer for transformer testing and a 400 kV matching transformer for shunt reactor testing. The system can be used to test both transformers and shunt reactors in accordance with IEC standards. These are the most important tests:
induced alternating voltage tests
measurement of open-circuit currents and losses
Short-circuit impedance and short-circuit loss measurements